Qualifications
Bachelor Degree University Negeri Sriwijaya Gpa 30.1 Majoring Electrical
Offshore Technology Instituted Gpa 8.96 majoring E&I Inspector
Career Summary
1 Period June 2014 – Present
Company Schlumberger
Position: QA/QC Engineer Electrical
Project: Schlumberger ,Exxon Mobile, MCL EOE, WelPad C,
Job Description:
Verify the installation & Cable ladder, cable tray conection to Control room, Main Circuit Center ( MCC ), I/O ESD Cabinet, I/O PCS Cabinet, Generator, Compressor, Dry, Cooler, Transfer Pump, Metering SKID, Chemical Injection, Separator, Crude Oil Pump, Flare, Knock out Flare, H2s Stripper Column, & gearbox against approved construction drawing
Safe and efficient operation of all electrical equipment and associated systems, including high frequency PMR work, documentation reporting and Log Keeping duties. 1st line maintenance, repair, inspection, fault finding on Power Generation and Distribution equipment ranging through High Voltage/Low Voltage/Extra Low Voltage Equipment throughout the Installation Topsides. The range of equipment includes, but is not limited to the following:
Low Voltage
– Power Distribution Systems including Emergency Power Generation, Switchgear, Motor Control Centres, Transformers, Motors, Cables, Battery Systems, Chargers and Associated Equipment.
Critical Power Distribution.
– UPS Systems, Battery Systems and Chargers and Associated Control Equipment.
Lighting and Small Power
– 110/240V Low Voltage Distribution, including Temporary Supplies, Control Circuits, Portable Equipment / Tools and Lighting.
Extra Low Voltage
– 24V D.C. Extra Low Voltage Distribution Systems and Power Supplies, including Battery Chargers and Battery Systems, Control Circuits, and interface with Instrument Control Systems.
EEx Equipment
– Responsible for ensuring the integrity of “Ex” explosion protected equipment throughout the platform.
The above equipment particulars with spesfications comply
Conduct Inspection of all Electrical & Instrument device’s according to class, owner specification and Standards (Merger Test, Continuity Loop Check, High Potential Test (HIPOT)and load test
Participate in generating Test Pack’s or Work Pack which related to E & I Work, based on specifications and standards that meet Client/Owner demand.
Check, Review Drawings & Monitoring installation and erection refer to construction drawing (Structure Drawings, Setting LV-MV Panel & other equipment)
To ensure Human Safety Environment Regulations applied in every steps of the E & I works
Verify all Inspection Test of all LV, MV cables, and other equipment E&I refer to the Test Pack’s or Work Pack’s.
To check while operating engine
a. For unusual noises,
b. Throtle operation,
c. Operation of gauges & safety controls
d. Air induction system
e. Exhaust System
SUPPORT WELD TESTING
>> To check shaft alignment after chock fast
>> To check the main engine & gearbox installation, tightening bolts wire
>> To check before starting engine ( adjust required )
a. Engine & accessories mounting
b. Fuel, Lube Oil or coolant leakage
c. Fuel oil Instalation
d. Lube Oil system Installation & Lube Oil Level
e. Cooling system Installation & Coolant Level
f. Air Cleaneer
g. Engine Breather
2. Period January 2014 – Present
Company Citra Shipyards
Position: QA/QC Engineer Electrical
Project : SPOB, Tugboat , CPO, Tanker,
Job Description:
Checking daily the installation cable & pipe connection to main engine & gearbox against approved construction draw
Safe and efficient operation of all electrical equipment and associated systems, including high frequency PMR work, documentation reporting and Log Keeping duties. 1st line maintenance, repair, inspection, fault finding on Power Generation and Distribution equipment ranging through High Voltage/Low Voltage/Extra Low Voltage Equipment throughout the Installation Topsides. The range of equipment includes, but is not limited to the following:
– Power Distribution Systems including Emergency Power Generation, Switch gear, Motor Control Centers, Transformers, Motors, Cables, Battery Systems, Chargers and Associated Equipment.
Critical Power Distribution.
– UPS Systems, Battery Systems and Chargers and Associated Control Equipment.
Lighting and Small Power
Extra Low Voltage12 – 24V D.C. Extra Low Voltage Distribution Systems and Power Supplies, including Battery Chargers and Battery Systems, Control Circuits, and interface with Instrument Control Systems.
EEx Equipment
Conduct Inspection of all E&I device’s according to class, owner specification and Standards (Merger Test, Continuity Loop Check, High Potential Test (HIPOT)and load test
Participate in generating Test Pack’s or Work Pack which related to E & I Work, based on specifications and standards that meet Client/Owner demand.
Check, Review Drawings & Monitoring installation and erection refer to construction drawing (Structure Drawings, Setting LV-MV Panel & other equipment)
To ensure Human Safety Environment Regulations applied in every steps of the E & I works
To check while operating engine
To carry out sea trial, All reading, to be record according sea trial procedure ( separate procedure)
Function of main engine alarm system
Test fuel oil transferring from FO tank to FO day tank using FO transfer pump
Enthusiastic and willing to advance in the position (Marine Ops/Operations WAM, OPITO Petroleum Open Learning Modules in Process Oil and Gas). Cross training and assisting Operations in equipment/plant/system start up, maintenance, monitoring and shutdown/start up.
3. Period April 2013 – January 2014
Company Saipem Indonesia
Position: QA/QC Engineer Electrical
Project : Fabrication platform & Offshor5e SKIDWAYS
Job Description:
Interpretation, Review and Check Specifications, Procedures, Code, Government Regulation & ITP (Inspection & Test Plan) for Modification
Directly responsible to the Company Site Representative on all engineering, planning, commissioning, material and all other technical service essential to support the construction activities at the offshore Work site
Prepared, Check actual and Executions Plant is a Process that has been developed as a result of Engineering Technical Integrity into the design, drawings, planning, certification, construction, commissioning, maintenance and operational activities of a facility.
Check actual & Review Installations Schedules Project.
Power Distribution Systems including Emergency Power Generation, Switch gear, Motor Control Centres, Transformers, Motors, Cables, Battery Systems, Chargers and Associated Equipment.
Critical Power Distribution.
– UPS Systems, Battery Systems and Chargers and Associated Control Equipment.
Lighting and Small Power
– 110/240V Low Voltage Distribution, including Temporary Supplies, Control Circuits, Portable Equipment / Tools and Lighting.
Extra Low Voltage
12 – 24V D.C. Extra Low Voltage Distribution Systems and Power Supplies, including Battery Chargers and Battery Systems, Control Circuits, and interface with Instrument Control Systems.
EEx Equipment
– Responsible for ensuring the integrity of “Ex” explosion protected equipment throughout the platform.
Coordination with subcontractor when apply job what should be do before installation and erection.
Prepared and monitoring material or Material Take Off (MTO) for installation.
Check, Review Drawings & Monitoring installation and erection refer to construction drawing (Piping & Instrument Drawing “P&ID”, Piping Plant, Isometric Drawing, Structure Drawings And Pipe Support ).
Verify material Carry Over raised by contractor due to material deviation and work out with Field Engineer to solve the problems.
4. Period Augustus 2011 – July 2013
Company NOK
Position: Supervisor
Project : Production Toshiba, Seagate, Western
Job Description:
Establishes production standards of efficiency, minimum wastages and maximum utilization of resources (machines, raw material and manpower).
Establishes and monitor for monthly and yearly reduce production cost as management director plan.
Establishes and monitor for continual improvement as monthly and yearly productivity improvement plan.
Supervises production processes to ensure implementation of company standards.
Prepares monthly production plans and obtains approval of Section Manager of production.
Coordinates with procurement officers to ensure smooth supply of raw materials.
Establishes quality control standards and procedures. Ensures strict adherence to those standards.
Supervises machines maintenance programs. Recommends machines modifications if needed.
Prepares monthly manpower plan. Makes sure all vacant positions are filled in coordination with section manager.
Establishes for continual improvement by regular Quality Control Circle (QCC) activity.
Prepares employees safety procedures and makes sure that these procedures are enforced.
Establishes and maintain all Production area practice good 5S.
Establishes Shipment schedule achieve target
Prepare Plan Consumable / forecast as schedule
– Review & Compile All Field Electrical Record for Project Documentation.
Control Cost Material
1. Prepare actual costing by project/item name
2. Material Control ( defective , drop part, Result testing and under New product )
3. Do Material Take Off (MTO)
4. Prepare Plan material and costing by project / Item Name
5. Prepare Plan & Result actual variance analysis
6. Establish MRP system
7. Able convert the costumer order to production
8. Make progress report, planning report and submit customs all to client.
9. Contact, correspondence and guide to client of all project data and information
10. Check Raw material availability in SAP
11. Program TCD ( total cost down )
12.Weekly inventory and Plus variance
13. QCC team
5.5 Period June 2010 – June 2011
Company FLEXTRONICS
Position: Supervisor
Project : Production Nexan
Job Description:
Understanding for overall B/E line operation per project basis.
Ensure hand load line run as per schedule.
Follow up and make sure completed shipping till to logistic.
Communicate with support team regarding any issue on Backend line.
Monitor leader and operator to achieve the set target, yield & UPH base on Tack Time given.
Together with Client Supv Conducted daily meeting to review the previous day performance with all the supporting team.
Ensure to meet shipment as per planning.
To ensure SPC chart was fill in all data including CA if required.
Monitor production scrap, component and PCBA through scrap review meeting.
Raise PDR if any deviation of process.
Raise LMF if any nonconformance material.
Control material issued base on daily usage.
Improving line performance, thru monitoring, evaluation and discussion with team (KAIZEN ACTIVITY).
Control all document (parameter, process instruction).
Summarize daily report from line leader (Performance and Inventory).
Brief and feedback to sub-ordinate regarding any issue in production.
Control material usage base on 3-4 hours production.
Housekeeping (5S- Basis).
Communicate for all information to other shift verbally and COMM_BOOK.
Control and monitoring for Over Time (OT).
Control equipment need at production.
Communicate with Client/owner regarding shipment required.
Organize his/her team (asstsupv, leader) for shipment achievement.
Provide daily report.
Conduct quality meeting with support team
Guidance:
1. Shipment Plan and Ramp from PA.
2. Line Run rate as per project basis (Test UPH)
3. Knowledge of Mapic System (M0#, Open Order, Stock Store, BOM, Issue – Un-issue – Over issue, ect)
6. Period December 2007 – December 2009
Company Mitsui Engineering & Shipbuilding Co. Ltd
Position:QC Inspector E&I
Project : MAN B&W S50ME-B
Job Description:
Identify and Rectify any mislead documents regarding Electrical & Instrumentation Work as a team.
Conduct Inspection of all Electrical & Instrument device’s according to Client’s specification and Standards (Merger Test, Continuity Loop Check, High Potential Test (HIPOT).
Participate in generating Test Pack’s or Work Pack which related to E & I Work, based on specifications and standards that meets Client/Owner demand.
Check, Review Drawings & Monitoring installation and erection refer to construction drawing (Structure Drawings, Setting LV-MV Panel & other equipment).
To ensure Human Safety Environment Regulations applied in every steps of the E & I works.
Verify all Inspection Test of all LV, MV cables, and other equipment E&I refer to the Test Pack’s or Work Pack’s.
Participate in Procedural tests to all E & I Equipments, such as: Loop Test, System running, Start Up.
Directly participate to the Site on all job executing, planning, commissioning, material and all other technical service essential to support the construction activities at the offshore Worksite.
Coordination with subcontractor, main contractor when apply job what should be do before Start Up and Simulation Test.
Check, Review Drawings & Monitoring installation and erection refer to construction drawing (Piping &Instrument Drawing “P&ID”, Piping Plant, Isometric Drawing, Structure Drawings And Pipe Support ).
Participate in Procedural test’s to all E & I Equipment’s, such as: Loop Test, System running, Start Up.
Coordination with subcontractor, main contractor when apply job what should be do before Start Up and Simulation Test.
Directly responsible to the Company Site Representative on all engineering, planning, commissioning, material and all other technical service essential to support the construction activities at the offshore Work site.
Verify material Carry Over raised by contractor due to material deviation and work out with Field Engineer to solve the problems.
7. Period April 2006 – April 2007
Company PT.AEI (Angkasa Engineers Indonesia)
Position: QC Inspector E&I
Project : TANBURUP
Job Description:
Identify and Rectify any mislead documents regarding Electrical & Instrumentation Work as a team.
Conduct Inspection of all Electrical & Instrument device’s according to Client’s specification and Standards (Merger Test, Continuity Loop Check, High Potential Test (HIPOT).
Participate in generating Test Pack’s or Work Pack which related to E & I Work, based on specifications and standards that meets Client/Owner demand.
Check, Review Drawings & Monitoring installation and erection refer to construction drawing (Structure Drawings, Setting LV-MV Panel & other equipment).
To ensure Human Safety Environment Regulations applied in every steps of the E & I works.
Verify all Inspection Test of all LV, MV cables, and other equipment E&I refers to the Test Pack’s or Work Pack’s
Participate in Procedural test’s to all E & I Equipments, such as: Loop Test, System running, Start Up.
Directly participate to the Site on all job executing, planning, commissioning, material and all other technical service essential to support the construction activities at the offshore Worksite.
Coordination with subcontractor, main contractor when apply job what should be do before Start Up and Simulation Test.
Check, Review Drawings & Monitoring installation and erection refer to construction drawing (Piping &Instrument Drawing “P&ID”, Piping Plant, Isometric Drawing, Structure Drawings And Pipe Support ).
Participate in Procedural test’s to all E & I Equipment’s, such as: Loop Test, System running, Start Up.
Coordination with subcontractor, main contractor when apply job what should be do before Start Up and Simulation Test.
Directly responsible to the Company Site Representative on all engineering, planning, commissioning, material and all other technical service essential to support the construction activities at the offshore Work site
Verify material Carry Over raised by contractor due to material deviation and work out with Field Engineer to solve the problems Rectify any mislead documents regarding Electrical & Instrumentation Work as a team.
Conduct Inspection of all Electrical & Instrument device’s according to Client’s specification and Standards (Merger Test, Continuity Loop Check, High Potential Test (HIPOT).
Participate in generating Test Pack’s or Work Pack which related to E & I Work, based on specifications and standards that meets Client/Owner demand.
Check, Review Drawings & Monitoring installation and erection refer to construction drawing (Structure Drawings, Setting LV-MV Panel & other equipment).
To ensure Human Safety Environment Regulations applied in every steps of the E & I works.
Verify all Inspection Test of all LV, MV cables, and other equipment E&I refer to the Test Pack’s or Work Pack’s.
Participate in Procedural tests to all E & I Equipments, such as: Loop Test, System running, Start Up.
Directly participate to the Site on all job executing, planning, commissioning, material and all other technical service essential to support the construction activities at the offshore Worksite.
Coordination with subcontractor, main contractor when apply job what should be do before Start Up and Simulation Test.
Check, Review Drawings & Monitoring installation and erection refer to construction drawing (Piping &Instrument Drawing “P&ID”, Piping Plant, Isometric Drawing, Structure Drawings And Pipe Support ).
Participate in Procedural test’s to all E & I Equipment’s, such as: Loop Test, System running, Start Up.
Coordination with subcontractor, main contractor when apply job what should be do before Start Up and Simulation Test.
Directly responsible to the Company Site Representative on all engineering, planning, commissioning, material and all other technical service essential to support the construction activities at the offshore Work site.
Verify material Carry Over raised by contractor due to material deviation and work out with Field Engineer to solve the problems.