Qualifications & Training
Turan-Profi International Professional Academy. Aug 2011 – Aug 2011
Atyrau city, Kazakhstan.
Training course -Fundamentals of Quality Management.
TENGIZCHEVROIL, Tengiz project. Atyrau, Kazakhstan. May 2011 – May 2011
Operation process zone access training.
Training centre YKK, Atyrau city, Kazakhstan. Jun 2010 – Jun 2010
Basic Offshore Safety Induction and Emergency Training (BOSIET).
State Technical University, Karaganda City, Kazakhstan. Sep 2001 – Jun 2007
Specialty: Industrial (Project) and Civil Engineer.
Economics and Business International School. Jun 2006 – Jun 2006
Astana city, Kazakhstan.
Training course- Technical supervision in construction
Career Summary
Fircroft Engineering Services Ltd Atyrau Branch
(TENGIZCHEVROIL LLP,CHEVRON). August 2013-Present
Tengiz, Kazakhstan.
QA/QC Inspector.
• Reports to Quality Manager and has responsibility to conduct receipt inspections of material/equipment and reviews documentation provided by the various suppliers.
• Examines the material/equipment upon arrival at the warehouse for in-transit damage.
Reviews material certificates for compliance
• Ensure timely completion of RCI’s and forward to CMS group in expeditious manner.
• Develop and publish NCRs and Surveillance Reports to identify and gain resolution of discrepancies observed during inspections of equipment/materials.
• Liaise with TCO Warehouse Ops PMI Coordinator to arrange PMI examinations on alloy materials.
• Ensure good housekeeping at all times and timely completion of actions to resolve safety issues.
• Employ Operational Excellence and Quality Team Values to achieve continuous improvement and performance excellence.
• Review and sign Position Description, and participate in team meetings to review progress and status of Quality and Project initiatives.
Almas-Semser LLP-Contractor of TENGIZCHEVROIL LLP.
May 2012 – August 2013
Tengiz project. Kazakhstan.
Technical Supervising Engineer.
Quality control and inspection of mechanical, piping and civil works.
• Quality control of manufacturing and installation of steel structures.
• Checking the Acts of Hidden Works Inspection, checking the General works log and Specific logs of separate activity types.
• Acceptance and delivery of work performed by the client.
• Preparation of inspection documentation.
• Coordination and review of design changes with the customer.
• Review Site Engineering Queries.
• Inspection of Pipelines and spools hydrotest.
• Quality control and inspection of materials.
• Quality control and inspection of installation pipe fittings.
TOZZI Company. Kashagan project. (offshore) Caspian Sea.
Jun2011 – May 2012
Engineer/Inspector Quality Control.
• Quality control and inspection of piping and welding works.
• Inspection of mechanical equipments.
• Perform a variety of flange joint related services, bolt torque and tensioning.
• Quality control of manufacturing and installation of steel structures.
• Inspection of the bolts pipe lines and fittings.
• Inspection of completeness and compliance project pipe parts.
• Acceptance and delivery of work performed by the client.
• Preparation of inspection documentation.
• Coordination of design changes with the customer.
• Checking the qualifications of specialists and workers.
“TNS” JSC -Contractor of TCO. Tengiz Project, Kazakhstan.
May 2011 – Jun 2011
Quality Control Engineer.
• Pre inspection and inspection welding, structural and painting works.
• Quality control and inspection of civil works, metal fabrication and painting.
• Organization and conducting certification of welders.
• Input control materials.
• Installation inspection and tightening of bolts of structural.
• Reinforcement and concrete work.
• Coordination of design changes with the customer.
• Providing technical specifications to head of construction supervisors.
CCC Company. Kashagan project. (offshore) Caspian Sea.
Aug 2009 – Apr 2011
Piping.
• Installation of pipes,installation and changing gaskets,
• Various of valves on the site in accordance with the specification and with isometric drawings.
• Selection and tightening bolts of pipe lines in accordance with the design and technical requirements.
• Testing and control of bolting and flanged connections, bolt torque and tensioning.
• Installing and replacing gaskets of pipe lines.
• Fabrication/Manufacturing pipe products in the pipe shop by engineering drawings.
• Hydro pressure testing of pipe lines.
Saulet Studio. Astana city, Kazakhstan.
May 2007 – Aug 2009
Design Engineer.
• Development of working drawings on AutoCAD.
KUAT CORPORATION. Astana city, Kazakhstan.Jul 2001 – Mar 2007
Foreman.
• Organization and management of construction works.
• Manufacture and installation of steel structures.
• Reinforcement and concrete work.
SIBSPETSREMONT JSC. Barnaul city, Russia.
Jan 1996 – Jul 2000
Welder-Fitter.
• Installation steel/structural details.
• Welding and assembly of high-rise buildings and parts of industrial plants.
• Work at height.