CV, Turkish International Civil Construction Engineer seeks work

Available
Serial No: 16504
Skills keywords: concrete, construction, earthworks, management, planning
Current location:  Pahang, Malaysia - View on map
Nationality: Turkish
Spoken languages: english, russian, Turkish

WORK EXPERIENCE

03.2014 –

PETRONAS MLNG – Marlin LNG Project (Linde Group, Malaysia)

Civil Construction Engineer

Civil Construction Engineer for Civil Works of BOG&NGU in Marlin LNG Project;

• Responsible to monitoring daily activities on site and reporting.

• Manage and organize subcontractors according to HSE, JHA and JMS Procedures.

• Liaison with Linde Engineering Department about design issues for ongoing works.

• Manage civil works according to Petronas Permit to Work system.

• Conducting inspection according to QC plans for releasing.

• Updating of the Construction Execution Plan.

• Control finishing work related Sub-station building.

• Ensure that site Design and Quality Verification information/document control is current and ensure that all responsibilities with regard to document standards and regulations are delivered.

• Review contractor’s Progress Reporting and provide standard project reports to site leadership.

• Maintain the risk register and update mitigations regularly ensuring adequate risk mitigation or contingency plans are in place.

• Attending Weekly Safety Walk down.

11.2012 – 01.2014

BP COMPANY – Baku Tbilisi Ceyhan Crude Oil Pipeline Project (BP Turkey)

Civil Construction Engineer

Civil Construction Engineer for Block Valve Stations Fortification Works, River Crossing Enhancement Works and Marpol Project;

• Responsible to monitoring daily activities on site and reporting.

• Manage and organize contractors and subcontractors according to HSE, MS-RA Procedures.

• Liaison with BP Project Department about procedures& drawings for ongoing works.

• Approving site interim monthly.

• Civil Site Representative for Marpol & Jetty Foam Line Project which has 3 ea. 4000 m3 Oily Water Slop Tanks, 2 ea. 125 m3 Bilge Water Tanks and approx. 7 km length 16’ and 6’ pipeline onshore and offshore.

• Ensure all construction engineering activities are achieved within schedule and comply with HSSE and Quality requirements.

• Responsible to manage contractors for civil activities according to BP & international standards.

• Giving comments at design phase for civil drawings and method statements.

• Responsible to develop overall QA/QC plans.

• Set and monitor progress against KPIs and intervene in a timely manner when corrective action is required.

• Participate in regular Construction/Engineering Interface meetings and participate in the resolution of design and engineering issues as they arise.

• To co-ordinate with the Quality group including the timely close out of STQ, NCRs.

• Conducting inspection on hold point for releasing.

• Attending Weekly Safety Walk down.

11.2011 – 10.2012

AIMROC – Chovdar Gold Mine Project (Proccea Construction Co., Azerbaijan)

Civil Site Superintendent

Responsible to establish and maintain work procedures on site and organize subcontractors according to weekly schedules.

• Organize daily activities on site and control all kind of civil and soil works according to HSE Management.

• Collecting daily progress reports from site crew and preparing progress diagrams and modify them if necessary.

• Determine schedules for workforce, material and equipment requirements.

• Manage and monitoring ADR Plant civil works.

• Supervise earthworks of Heap Leach and Ponds Area and organize subcontractors according to two week look ahead schedule.

06.2011 – 11.2011

ULKER GROUP – Guzide Ulker High School Project (IPROM Insaat, Turkey)

Construction Engineer

Responsible to supervise and monitor all kind of civil works and soil works on site in accordance to with drawings and specifications.

• Organize subcontractors in according to weekly schedule.

• Revise drawings with consultant’s advice.

• Manage to set all official documents in accordance with government.

• Procure materials and equipments requirement on site.06.2007 – 06.2011

AGIP KCO – Kashagan Development Project (SKA Insaat-SATYAPI, Kazakhstan)

Civil Site Lead Engineer

Responsible to establish and maintain procedures and guidelines for inspection with a crew of 200 workers, 3 supervisors and 5 foremen including and coordinate between client (AGIP KCO), contractors (GATE, CCIC, Sicim, Bonatti and ISKER) and site.

• Set up and mobilization process of civil works including backfilling and excavation – approximately 500.000 m3 – for all areas (sulphure plant, gas plant, oil plant, KIB and KPP) for GATE Company.

• Supervising of all kind of civil works that includes all kind of foundations, buildings, trenches -10.000 m3- for GATE Company

• Supervising of civil works for Water Treatment Facilities of GATE Company.

• Production of precast elements (manholes, catch basins, trenches…) for GATE Company

• Superintending of all kind of civil works of Site Facilities of CCIC Company.

• Supervising of all kind of civil works for Field Temporary Refuge Building for ISKER Company.

• Supervising of infrastructure of roads-approximately 5 km- in site for ISKER Company

• Preparing field change notices, extra work orders and back charge notices.

• Attending Zero Accident Team Meetings for implementing safe work on site. More than 4.000.000 hours without lost time accident.

• Preparing projections and schedules for workforce, material and equipment requirements.

• Maintaining records of costs and quantity information, evaluating data and preparing applicable reports as requested by project management.

08.2005- 02.2007

TOKI – Residential Complexes (KC Group, Turkey)

Technical Office Engineer

Responsible to provide site supervision, planning, man power control and material requests during construction of residences on site.

• Organizing day to day activities of the client (TOKI- Housing Development Administration Of Turkey) and subcontractors workforce through the appropriate supervisor or foreman,

• Supporting the construction manager in determining and defining Client and Subcontract planning by preparing detail work activity sheets on a weekly basis for 4 weeks look ahead,

• Executing the work in accordance with the contract scope of work, drawings, specifications, and program.

• Ensuring the site operations are conducted safely without harm to personnel or the environment by following HSE procedures and good working practice.

• Submitting daily progress and manpower reports to the planning engineer,

• Preparing monthly payment certificates and follows up.

EDUCATION

Erciyes University -Engineering Faculty Civil Engineering Department (2000-2005)

FOREIGN LANGUAGES

Turkish – Native

English – Advanced

Russian – Basic






popup-img