Relevant Qualifications & Skills
Academics:
B.sc Electrical Eng
2005 – 2009
1st Punjab University, Lahore
Languages:
Urdu Expert More than 10 years 1 month or less
English Expert More than 10 years 1 month or less
Arabic Beginner More Than 2 Years 1 month or less
Skills:
ETAP Good More than 6 months 1 month or less
AutoCAD Good More than 1 years 1 month or less
Optimal Tower Cad Good More than 1 years 1 month or less
MS Project Good More than 1 years 1 month or less
MS Office Suite Expert More than 5 years 1 month or less
Primavera P6 Good More than 1 years More than 1 years
Professional Memberships:
Member of Saudi Council of Engineers (SCE)
Member of Pakistan Engineering Council (PEC)
Career Summary
1- SCAN ELECTROMECHANICAL CONT. CO. LLC SHARJAH UAE
JUNE 2014 – PRESENT
PROJECT:
E34/2013 132kV Cabling Works in Northern Emirates
Position: Project Engineer
Key Role:
1) As per FEWA Technical specification, prepared and reviewed the following Plan & Drawings and submitted to FEWA:
Detailed design drawings and construction drawings of the Cable Routes and the joints locations
Details of Road crossing types & locations
Proposed sheath earth bonding schematic diagram
Proposed method of cable laying and calculate cable pulling tension and side wall pressure of the each section of the cable route ROW
2) Before starting site works, prepare the following documents:
Arranged and obtain work permits, regulations, instructions from concerned authorities
Put in place all the guarantees requested by the different local authorities.
Obtained the approval for the Authority (FEWA) and will distribute the approved drawings to the concerned Local Authorities in order to get the “No Objection” for the works along the cable routes
Conducted the tracing of the cable route along the approved reservation upon receipt of the No Objection Clearances (NOCS) from the various local Authorities and prior to the commencement of excavation
Method statements for performing any works
HV cable and FO cables Site Acceptance Test (SAT) formats & methods submitted to FEWA for approval
3) As per FEWA requirement , do the following necessary works on site:
Carried out the final surveys of the cable route and prepare the corresponding drawings in a form agreed by Authority (FEWA) / Engineer and provided a survey report
Peg out the centre line of the proposed cable corridors at regular intervals and prepared the drawings
Excavations to the required dimensions (1.2 m deep x 2.5 m width) and as agreed with Authorities made for installation of precast concrete troughs and shuttering and dewatering of the cable trenches, as well as the preparation of the cable ducts and supporting structures for installation of the cables
Pre cast concrete trough (700 mm x 2000 mm) for cable laying installed under our supervision by sub contractor
Installation of cables comprise of 2 circuits of three XLPE cables 132kV, 1c x 1200 mm2 in trefoil formation plus one number 32-fibre optical cable per each circuit laid in a common precast concrete troughs. Cables laid directly from the drums into the troughs and special rollers placed at close intervals (maximum 2 meters) employed for supporting the cables while pulling and laying them
Placing the trough covers, backfilling with excavated soil with warning tape placing at required depth, watering & compaction of back filling in layers
Placing of approved cable route markers at maximum 50.0 meters intervals (2 Nos. markers at each location). The works also include any reinstatement like interlock tiles, asphalt or concrete etc. surfaces to the satisfaction of concerned Agencies. The work included provision of 6 Nos. of crash barriers for each Joint bay; the location of the Joint bay marker has to be approved by the FEWA / Engineer
At highways and heavy traffic roads and at locations where Municipality does not permit crossing by open cutting, the crossing done by Horizontal Directional Drilling Method (HDD) or micro tunneling. 8 Nos. of HDPE ducts are installed.
Installation of 132kV cable straight through joints along with coffin boxes required for single core cables suitable for the cable, 1200sqmm, XLPE including all temporary supports required at site
Installation of cross bonding or earthing link box for all joint location and each one suitable for earth bonding of sheaths of single core 132kV, 1200sqmm, XLPE cables. The cross bonding link boxes are suitable for outdoor installation moisture proof, dust proof and mounted inside a concrete enclosure with suitable manhole cover to access inside. The cable metallic sheaths directly earthed through link boxes at every third joint bay. At the intermediate joints the sheaths earthed through voltage limiters to limit steep-fronted transient over voltages to a value which can be safely withstood by the sheath insulation. The voltage limiters shall be made of non-linear resistors
The circuit markings provided for each link box with phase markings for each cable. Suitable earth rods/spikes are driven at minimum two locations for earthing
Installation of standard waterproof underground optic fiber cable splicing kit for 32 fibers and splicing of fibers of optic fiber cable
Testing and commissioning of two FO Cables before and after splicing performed as per FEWA standard & specification. Further SAT Tests for FO Cables conducted by FEWA approved FOC Cable Test Engineer. The spare FO cable tested end to end and looped safely
The site testing is inclusive of performing of all site tests listed in the FEWA standards and specifications for 132kV cables and accessories including line surge arresters. AC HV Site Test shall be properly coordinated and done under supervision of GIS manufacturer. All Site Acceptance Test (SAT) conducted by FEWA approved Test Engineer and in the presence of cable, joints and GIS manufacturer representative. All test procedures and test forms are to be submitted and approved by FEWA. All test instruments and equipments used shall have valid calibration certificate. All electrical site tests carried out in the presence of FEWA / Engineer
PROJECT:
SHARJAH INTERNATIONAL AIRPORT NEW RUNWAY 250 m SEPARATION AIR SIDE
Position: Electrical Engineer
Key Role:
Apply the SLD on ETAP and study load studies, short circuit analysis and propose relay settings
Cable ampacity , size calculations , cable laying and pulling tension calculations for LV and MV cable laying
Study and prepare of Single Line Diagram of 11 kV Substation and Distribution system as per consultant specification
Installation of 4 numbers 1000 kVA and 8 numbers 50 kVA step-down transformers
Installation of 4 numbers 100 kVA step-up transformer
Installation of 11 kV RMU of Schneider Electric
Installation of 4 numbers LV 780 kVA backup generators
Installation of 4 numbers UPS ( UBT Piller make) 368 kW for backup
Installation of FO, LV and HV cables
2- ARABIAN BEMCO CONTRACTING CO. (LTD) / INMA UTILITIES CONTRACTING CO. (LTD) (BINLADIN GROUP) February 2012 to June 2014
PROJECT:
KING ABDUL AZIZ INTERNATIONAL AIRPORT, JEDDAH, SAUDI ARABIA
Position: Electrical Engineer
Key Role:
Worked as Electrical Engineer for the implementation of Electrical Works on Load Center which controls and provide Electricity to KING ABDUL AZIZ INTERNATIONAL AIRPORT,JEDDAH
Review/Study of Design Drawings and Shop Drawings
Review/Study the Electrical standards of the project from the client i.e. NEC, IEC etc
Study the quality and safety standards of work
Study the catalogs of the materials
Calculate BOM/BOQ and take off of material
Execution and completion of electrical work accordingly to civil work and latest shop drawings
Make list of materials required everyday and make a request to issue material from the store
Make As build drawings
Completion of work request/QC Department/Consultant inspection
Coordinate with civil and mechanical engineers and prepare coordination drawings
Coordinate with low current engineers for low current electrical works
Coordinate with QC and safety department for the safe and standard work
Participate in site daily/weekly progress meeting with client
Make execution and completion plans
Manage 100 site personnel for work execution
Make daily and weekly progress report of the work done
Provide safety and quality trainings on site
Installation and termination of 13.8 kV metal clad switchgear with ACB circuit breaker and OCEF relay ABB make
Installation and terminations of 13.8 kV oil type and dry type transformer ABB make
Installation and pulling of MV cables and LV cables
Installation and termination of MDBs, SMDBs, DBs
Installation of battery system and battery racks
Installation , termination and wiring of power sockets, lighting switches, wall and hanging lights, low current system
Installation of cable ladders, cable trays & cable trunk raceways for MV and LV cables
Installation of PVC, EMT and RGS conduit for wiring raceways of small power sockets, lighting switches, lighting points, grounding and lightning protection
Installation of grounding system for MV/LV system and equipment Earthing
Installation of lightning protection system for equipment and building structure protection
Installation of PVC & GI boxes for power sockets, lighting switches, wall and ceiling lights, grounding
Installation of Earthing pits for grounding and lightning protection
Installation Earthing of MV cables , cable ladders, cable trays, power sockets, lighting switches, wall and hanging lights
3- NATIONAL DEVELOPMENT CONSULTANTS (PVT) LTD (NDC) Lahore, Pakistan
(JV Nippon Koei Japan/Dolsar Turkey Consortium)
November 2011 – February 2012
PROJECT:
CONSULTANCY SERVICES FOR DESIGN, PREPARATION AND IMPLEMENTATION OF 4320 MW DASU HYDROPOWER PROJECT
Position: Design Engineer Transmission Lines
Key Role:
Review feasibility study report and Load flow studies
To collect data and prices of power equipment, auxiliary switchgears and accessories for AIS and GIS substations
To assist for design of GIB Power transmission line between main transformers in the underground power station to the outdoor switch yard, line and substation equipment BOQs
To collect prices from relevant WAPDA contracts/projects and multinational manufacturers of power house, 500 kV transmission lines and substations for cost estimation
Short circuit and load flow studies of power house
General & Particular technical specifications, technical data sheets and drawings
To assist for formatting of documents and drawings
4- ENGINEERING AND MANAGEMENT ADVISORY SERVICES (PVT) LTD (EnMasse) Lahore,Pakistan
June 2011 – November 2011
Position: Design Engineer Electrical
Key Role:
Load Flow studies and short circuit analysis
External Electrification of Housing Schemes
ELR and Feeder Analysis of existing and new feeders
Define the Corridor Right of way 132 kV underground cable
Satellite Survey of 132 kV underground cable using Google Earth, SOP GT Sheets and SUPARCO Images
Coordination study of 132 kV cable corridor with Environmental and Geological Engineers
Design and calculation of 132 kV cable ampacity, size, laying and pulling tension
Define cable laying standards
5- MIRZA ASSOCIATES ENGINEERING SERVICES (PVT) LTD Lahore, Pakistan
(In consortium with SMEC Australia, PB UK & SOGREAH France)
January 2010 – May 2011
PROJECT:
Feasibility Study for Evacuation of Power from Hydropower Projects
(BASHA, BUNJI and DASU) on River Indus and its Tributaries in Northern areas 500kV
Position: Design Engineer Electrical
Key Responsibility:
Define the Corridor Right of way
Satellite Survey of Transmission Line using Google Earth, SOP GT Sheets and SUPARCO Images
Spotting the tower through Google Earth
Write down the coordinate of each spotting tower
Convert the each spotting position in to Auto Cad drawing with the help of Global Mapper
Arrange the each spotting location on Google Earth after the horizontal alignment
Making the surface profile through optimal tower cad
Arrange the each tower vertically
Preparation of Survey Reports by using MS-Office