FROM 15.04.2013 TO 21.08.2013

Worked with Target Engg. Abu Dhabi as estimation engineer since 14.04.2013 , looked after estimation of mega oil and gas projects worth 1-3 billon usd for clients like SAUDI ARAMCO, GASCO ADCO ETC.

Completed GASCO HABSHAN PIPING REPLACEMENT PROJECT ESTIMATION.
Completed SAUDI ARAMCO CLEAN FUEL AROMATICS PROJECT MECHANICAL ESTIMATION
Completed ADCO PIPELINE PROJECT MECHANICAL ESTIMATION FOR TECHNICAS SPAIN.

04.01.2012 TO 04.04.2012

Ms PETRO ENERGY SUDAN, THRU, JAYETHE PETROTECH , ABU DHABI AS LEAD MECHANICAL ENGINEER

Involved in review of drawings, equipment data sheets , pfds , review of costing for piplines equipments data sheets are for all mechanical equipment data sheets for oil field equipments such as pressure vessels, heat exchangers, pumps, compressors etc

08.02.2011 TO 09.06.2011

Ms ATV PROJECTS INDIA LTD  as estimation manager for estimation of pressure vessels and exchangers

23.03.09. TO 22.06.09

M/s Costain Abu Dhabi Co. W.L.L. – Abu Dhabi  as Sr. Estimation Engr.

Engaged in oil & gas projects estimation. Worked on following projects.
Replacement of flare structure fabrication and painting for ADGAS –DAS OIL FIELD( SS 304 Fabrication )
Fabrication & Erection of 3 k.m. long piping for GASCO , HABSHAN. ( CS Piping ) value around 24 million AED.
Repair and refurbication of 23 nos LARGE DIA oil storage tanks for TAKREER, RUWAIS REFINERY.

02.11.08 TO 15.03.09
M/s L&T KUWAITAs Estimation Manager

Estimation of oil and gas projects such as tankages, plant piping etc.

Since 28.05.2007
M/s Lurgi India Pvt. Ltd., NEW DELHI As Lead Estimation & Costing

Nature of duties-
1 Estimation of Equipments and Manhour Estimation & complete plant estimation for process plant ( completed estimation of 1200 TPD Methanol Plant ) Using Icarus Design / Estimation Software for Mechanical Equipments.
2 Licensor cost evaluation.
3 +/- 5, 10% cost report preparation for the project.
4 Preparation of Proposals for the complete process plants.
5 Floating Enquiries, analysis of offers received from vendors in consultation with engg. Dept. , raising queries and try to get complete offer from vendors without any exclusions.
6 Comparing various offers.
7 Selection of vendors / contractors
8 Compiling various offers and putting their values in excel based software and to calculate the cost of project.
9 Estimation of Equipments and Manhour Estimation & complete plant estimation for process plant ( completed estimation of 1200 TPD Methanol Plant ) Using Icarus Design / Estimation Software for Mechanical Equipments.
10 Licensor cost evaluation.
11 +/- 5, 10% cost report preparation for the project.
12 Preparation of Proposals for the complete process plants.
13 Floating Enquiries, analysis of offers received from vendors in consultation with engg. Dept. , raising queries and try to get complete offer from vendors without any exclusions.
14 Comparing various offers.
15 Selection of vendors / contractors
16 Compiling various offers and putting their values in excel based software and to calculate the cost of project.

Sept 2005 TO Jan 2006
M/S MEDGULF CONSTRUCTION CO. W.L.L., DOHA, QATAR (CLIENT- QATAR PETROLEUM) As Construction Engineer

Nature of duties-
1 Construction supervision and management of fire water piping works for L.N.G. tanker loading berth at Ras Laffan area of Qatar
2 Planning for men, machines and materials
3 Execution of works as per DRGS. And Q.P. standards4 Review of Isometric DRG. study these in conjunction with P.A.D. and P&ID
5 Find out any mismatch among these DRGS. And get the matter resolved thru projects

Aug  2004 to Feb 2005
M/S APC INTERNATIONAL FZC, UAE (DEPUTATION TO B.I.P.C., AN IRAN GOVT. COMPANY)
Specialist Piping Engineer / Project Engineer – VCM Revamping Project

Nature of duties-
1 Responsible for finding out old data sheets of various static, rotary equipments & piping which are to be replaced with new one
2 Preparing fresh data sheets
3 Floating enquiries, making comparative statement of offers received
4 Selection of vendors
5 Execution of project after receipt of equipments and materials
6 Coordination with projects department

Feb 2004 to April 2004
M/S ANABEEB LTD., SAUDI ARABIA As Senior Cost Estimator

Nature of duties-
1 Responsible for estimation & bid preparation for turn around project of refineries, petrochemicals & fertilizer plants in Saudi Arabia as well as in other gulf countries
2 Estimation of tenders for minor/major shutdown activities or modification required in plants such as replacement of vessels internals, tanks cleaning and tanks repair works etc.

Nov 2003 to Jan 2004
M/s IOTL
Site manager at IOCL PANIPAT REFINERY for Tankage construction project.

May 2002 to October 2003
M/S HITECH ENGINEERS, AONLA, BAREILLY
Site In charge

Nature of duties-

1 Responsible for complete site handling for fabrication, erection, testing, commissioning of two nos. naphtha storage tanks and shut down jobs of IFFCO, ANOLA plant. Major responsibilities include deployment of labor, envisage the requirements of men, machines & materials, billing, coordination with client, responsibility for correctness of fabrication/erection/testing/commissioning of tanks and shut down jobs.

Feb 2001 to April 2002
M/S SPECIAL TECHNICAL SERVICES, MUSCAT (OMAN)
Design Coordinator
2  Coordination with client & design contractor, approval of drawings from client, rectification of drawings from design contractor, monitoring progress of flow lines.

Assignment undertaken:

Design coordination for construction of flow lines for high-pressure gas, oil & water wells in OMAN.

June 1994 to June 2000
M/S ENGINEERS INDIA LTD., INDIA , Senior Engineer

Nature of duties-

3 Construction supervision & management
4 Inspection at various stages of construction
5 Monitoring & follow-up with contractors.
6 Inspection during construction, erection, hydro testing, pre-commissioning stage
7 Checking specification compliance
8 Checking extra claims
9 Progress monitoring & reporting
10 Coordination with various agencies, incoming material inspection
11 Fabrication, erection of tanks, piping, static & rotary equipment
12 Involved in N.D.T. examination of oil storage tanks, oil piping & structural works.

Assignments undertaken:

Mathura Refinery Project – Mathura
Involved in construction of hydrogen generation unit and hydrocracker unit. Materials involved were C.S, LTCS , STAIN STLL , LOE AND HIGH ALLOY STEELS.
U.P. Petrochemicals Complex – Pata
Construction of above ground piping works for GAS PROCESSING unit.
Marketing Terminal of I.O.C.L. – Sangrur, Punjab
Construction of oil marketing terminal of I.O.C.L. at Sangrur, Punjab. Activities involved were construction of tank ages, plant piping, manifold pump house, truck loading gentry, fire water system, foam system, commissioning

April 1989 to June 1994
M/S ATV PROJECTS INDIA LTD., INDIA, Engineer

Nature of duties-

1 Estimation of pressure vessels, heat exchangers, tank ages, plant piping
2 Preparation of bids
3 Construction supervision
4 Inspection at various stages of construction
5 Coordination with clients and contractors
6 Involved in N.D.T. examination of oil storage tanks and piping

Assignments undertaken:
Business Development / Contracts (May 1992 to June 1994)
Estimation and tendering of process equipments, preparation of documents for registration with clients, coordination with clients regarding technical/commercial matters related to contract.
Project Execution (May 1989 to April 1992)
Involved in construction supervision of 14 nos. of oil storage tanks built as per API 650 and associated piping works of national dairy development board’s Patparganj and Narela terminals in Delhi.
Involved in execution of giant fabrication shop of ATV PROJECTS having two bays of 155 meter * 26 meter each and commissioning of cranes.