Qualification
Degree in Building Management. Diploma & Certificate in Building Site Management, ISPE Swimming Pool Engineers CIOB, and IFM part 1 & part 2. CSCS Card, 5 Day SMSTS, First Aid Arbor Shoe South Ridge, SC
TYPE OF PROJECTS: New Build/ Industrial/Commercial Public and Private Sector, Roads, Design & Build of Swimming Pools, Social & Spec Housing, Refurbishment, and General Construction.
Positions: Project Manager/ Construction Manager & Site Manager
Now looking for work
I have the experience that you are looking for, I have worked on many varied projects from conception to completion, working for both Client and contractor, I’m looking to further my career with new challenges. Below are just some of the contracts that I have been involved with. If you require further information please contact me
Aug/Sept2013 (5wks) Site Manager assisting Project Manager for Persimmon Homes on a new Housing Estate Great Barr. To insure all new plots achieved NHBC Certs, and day to day operations.
July/Aug 2013 (4wks) Site Manager: Thomas Vale Construction: Extension to High School in Halesowen. Works to include Diverting Existing Drainage, Foundations and Brickwork to DPC and installation of new Glass ans Steel Canopy. To Manage sub-contractors H&S, RAMS and to oversee day to day operations. To liaise with the Estates Manager.
June/July (5wks) Site Manager: Wates Retail Asda Corby.
To manage Fit Out of new Café/Restaurant. Value 1.7 million.
To Manage Shop fitters and M&E Sub-Contractors. RAMS, H&S, Quality and to insure that the store could Open the next day (night work)
May 2013 (8wks) Site Manager: Wates Living Space. Evesham Worcestershire. To Manage Ground Works for 22 3 and 4 bed homes. Works to include: Site Clearance, Access Rds, and Foundations to DPC, Drainage, and Service. Also RAMS, H&E, Material req, Site Diary & Site Inductions
March 2013 Site Manager G&K Allied Bakeries West Bromwich.
Form opening/Tunnel in existing Structure, To Demolish Existing Steel Portal Frame/Cladding/Roof and all associated works.
To pour new Foundations, Column Bases, and Break into Existing Deep Drainage. To Erect Steel Structure, Cladding, Roofing. To lay new Power Floated Slabs, New Services and Install new Plant Equipment
Sept 2012 to December 2012 Site Manager Halifax Bank, Leek Havelock. To Manage Night Works to Live Bank to Include Removal of Asbestos Old Furniture. To install New IT, Counter Tops, Furniture, Floor Finishes and Decoration throughout. (on budget, programme and zero defects)
Aug 2012 to date Site Manager Kier Construction, Oxford, New Build British Gas HQ
External package Value £7million
To Snag External Envelope to include Brickwork Glazing, Rain Screens, and Flat Roof Structure (holiday cover)
June 2012- Aug 2012 Site Manager Wates Retail Halifax bank. To Manage Night Works to Live Bank. (As Above)
Feb 2011-May 2012 Site Manager Styles& Wood. To Manage Night Works to 6 NatWest Banks across South Wales
Dec 2011 For 6 weeks voluntary work on an orphanage in Nayhururu Kenya. Hands on Constructing a Treatment Plant
Sept2011 to Dec 2011
Fit out Barclay’s Banks, Styles & Wood South Wales, Kent and the south west( As Above)
Jan 2010 to July 2011
Freelance Site Manager(Agency Temp cover) Sheppard’s (Bourneville college)
Casey B’ham city centre, Seddod (Kineton Warwickshire) Greswolds(loughbrough)
Wates(Walsall)& NMC(Dudley)
Oct 08 to Aug 10
Site manager – Integrated Designs
New Build & Refurbs of Nursing homes West Midlands.
Value: 140k to 1.2m
Responsibilities: Overall daily control of sub contractors, H&S, Client liaison, O&M and QA
Nov 07 to Sept 08
Senior Site Manager – Willmott Dixon Ltd
Project: New Build £20 Million 650 seated theatre – Shrewsbury
Contract period 14 months
Roles & Responsibilities
• Brick Block & architectural stone work
• Temporary works, Scaffold, roof works, curtain walling & glazing
• zinc cladding
• To include H & S method statements risk assessments & general day to day running of the above packages.
• Reporting to Project Manager
Aug 07 to Nov 07 Project Manager Civils1 Manor Hospital Walsall
Skanska
Roles & Responsibilities: Works prior to PFI, Construction of new Sub Station
Excavation of deep drainage, Construction of new steam duct & Divert existing
LV HV & data cables
Reference: Project Manager Bernard Eland – Skanska
April 07 to Aug 07 Senior Site Manager: – OCON Construction
Roles & Responsibilities: To complete internals from 7th to ground
Project: (17 storey) 600 student accommodation
Value: 21 Million
Jan 07 – April 07 Night Manager: – Belfour Beatty Queen Elizabeth Hospital Birmingham
Roles & Responsibilities:
Night Manager overseeing concrete pours & power floating also to manage slip form
Oct 06 – Jan 07 Night Manager: – Paragon
Roles & Responsibilities
Night Manager overseeing internal demolition.
Project: Refurb 6 storey office block
Value: 6 Million
Dec 05 – Oct 06 Senior Site Manager/Package Manager: – Bluestone
Roles & Responsibilities
To oversee brick & block work to 2No. 5 storey buildings,
Value: 17.2 million / Package value 6.5 million
Project: 609 Student apartment / accommodation blocks
Precast planks + structural topping.
2No tower cranes,
Scaffolding, Lightweight structure to roof
January 05 – Dec 05
Jan 05-Dec05 Project Manager – Aston Christian Centre (Registered Charity) –Birmingham
To refurb. 2 existing factory unit into youth community and worship centre to incorporate fully functional I.T office suite, commercial kitchen, youth and Community area to first floor worship Hal. Construction consisted of major alterations to internal structures, to incorporate new DDA regulations, full electrical and mechanical overhaul to include complete new air and heating systems. New roofing redesign of drainage systems, finished article waiting /reception area, 2 new steel staircases design of Baptist pool oversee all sub-contract packages and payments
Value: 1.2 million
Duration: 36 Weeks
NB: due to charity status client (ACC) had restricted funds remit to save as much money as possible this was done by using local unskilled labour to subsides sub-contract labour percentage of savings to be agreed.